haya.Learning made clear
Unit III · Mathematics of finance
8 min readConcept sheetShort calculation; 10-mark investment (NPV) decision

Present value and discounting

Present value works backwards from a future sum to its worth today: divide by (1 + i)ⁿ. A positive NPV means a project earns more than the required rate.

Present valuePV = A ÷ (1 + i)ⁿ
Discount factor1 ÷ (1 + i)ⁿ
Net present valueNPV = PV of inflows − cost
Decision ruleAccept if NPV > 0

Why a rupee today is worth more

A rupee today can be deposited to earn interest, so it grows to more than a rupee later. To compare money at different dates, bring every amount to one date, usually today. Moving money back in time is called discounting.

Present value formulas

Present value of a single sumPV = A(1 + i)^(−n) = A ÷ (1 + i)ⁿ
Discount factorv = 1 ÷ (1 + i)ⁿ
PV of several cash flowsSum of each flow × its discount factor
Net present valueNPV = Σ PV of inflows − initial outlay
DecisionNPV > 0 accept; NPV < 0 reject

Discount factors at 10% a year

Years (n)12345
1 ÷ 1.1ⁿ0.90910.82640.75130.68300.6209

Present value of a single sum

Problem

You will receive Rs. 500,000 in 4 years. At 10% a year compounded yearly, what is it worth today?

Working
  1. PV = A ÷ (1 + i)ⁿ = 500,000 ÷ 1.1⁴.
  2. 1.1⁴ = 1.4641.
  3. PV = 500,000 ÷ 1.4641 = 341,506.73.
  4. Check: 341,506.73 × 1.4641 = 500,000 (to the nearest rupee). ✓
Answer

Rs. 341,506.73

Comparing two offers

Problem

A buyer offers Rs. 1,000,000 now, or Rs. 1,250,000 in 3 years, for a plot of land in Kurunegala. Money can earn 8% a year compounded yearly. Which offer is better?

Working
  1. Bring the later offer to today: PV = 1,250,000 ÷ 1.08³.
  2. 1.08³ = 1.259712.
  3. PV = 1,250,000 ÷ 1.259712 = 992,290.30.
  4. Compare: Rs. 1,000,000 now is more than Rs. 992,290.30.
Answer

Take Rs. 1,000,000 now; it is worth Rs. 7,709.70 more in today's money.

Net present value of a project

Problem

A Galle hotel can spend Rs. 2,000,000 on a renovation that brings extra cash of Rs. 800,000, Rs. 900,000 and Rs. 1,000,000 at the end of years 1, 2 and 3. The required rate is 12%. Should it go ahead?

Working
  1. Year 1: 800,000 ÷ 1.12 = 714,285.71.
  2. Year 2: 900,000 ÷ 1.2544 = 717,474.49.
  3. Year 3: 1,000,000 ÷ 1.404928 = 711,780.25.
  4. Total PV of inflows = 714,285.71 + 717,474.49 + 711,780.25 = 2,143,540.45.
  5. NPV = 2,143,540.45 − 2,000,000 = 143,540.45.
Answer

NPV = +Rs. 143,540.45, so the renovation is worth doing at 12%.

In Sri Lankan business

When a Sri Lankan group such as John Keells weighs a new hotel or plant, the standard method is to compare the present value of future cash flows with today's cost. A positive NPV supports the investment.

Exam angle

Short answer: “Find the present value of Rs. 121,000 due in 2 years at 10% compounded yearly.” 121,000 ÷ 1.21 = Rs. 100,000.

Structured question: “Rs. 1,000,000 now or Rs. 1,250,000 in 3 years at 8%? Advise.” PV of the later sum = Rs. 992,290.30, so take Rs. 1,000,000 now.

Essay: “Find the NPV at 12% of a Rs. 2,000,000 project returning Rs. 800,000, Rs. 900,000 and Rs. 1,000,000 over 3 years, and advise.” PVs total Rs. 2,143,540.45; NPV = +Rs. 143,540.45; accept.

Remember it

Future → today: divide by (1 + i)ⁿ. Today → future: multiply. Higher rate or longer wait means smaller present value.