Unit IV · Accounting, costing and financial management
10 min readConcept sheetMCQ · variance sums with the right sign

Standard costing and variance analysis

Standard costing sets predetermined costs and compares them with actual costs. A variance is favourable when actual cost is below standard, and adverse when above.

VarianceStandard cost for actual output − actual cost
Favourable (F)Actual cost below standard cost (or actual revenue above budget)
MaterialCost variance = price variance + usage variance
LabourCost variance = rate + efficiency + idle time variances

The standard costing cycle

Only significant variances go to managers for action.

Material and labour variances

VarianceFormulaUsually answerable
Material cost (MCV)(SQ × SP) − (AQ × AP)Total of price and usage
Material price (MPV)AQ × (SP − AP)Purchase department
Material usage (MUV)SP × (SQ − AQ)Production department
Labour cost (LCV)(SH × SR) − (AH paid × AR)Total of rate, efficiency and idle time
Labour rate (LRV)AH paid × (SR − AR)Personnel; wage agreements
Labour efficiency (LEV)SR × (SH − AH worked)Production supervisor
Idle time (ITV)SR × idle hours; always adverseProduction planning, maintenance

Reading the signs

  • SQ and SH mean standard quantity and standard hours for the actual output, not for the budgeted output.
  • Compute standard − actual: a positive answer is favourable (F); a negative answer is adverse (A).
  • Material usage variance splits into mix and yield variances.
  • A favourable price variance from cheap, poor material can cause an adverse usage variance, so read variances together.
  • Management by exception: attention goes only to significant variances.

Material variances

Problem

Standard: 2 kg per unit at ₹10 per kg. Actual output 1,000 units, using 2,100 kg bought at ₹9.50 per kg.

Working
  1. SQ for actual output = 1,000 × 2 = 2,000 kg; standard cost = 2,000 × 10 = ₹20,000
  2. Actual cost = 2,100 × 9.50 = ₹19,950
  3. MCV = 20,000 − 19,950 = ₹50 (F)
  4. MPV = 2,100 × (10 − 9.50) = ₹1,050 (F)
  5. MUV = 10 × (2,000 − 2,100) = −₹1,000, that is ₹1,000 (A)
  6. Check: 1,050 (F) − 1,000 (A) = ₹50 (F)
Answer

MCV ₹50 F = MPV ₹1,050 F + MUV ₹1,000 A.

Labour variances with idle time

Problem

Standard: 3 hours per unit at ₹20 per hour. Actual output 480 units. Workers were paid for 1,600 hours at ₹21 per hour, of which 100 hours were idle.

Working
  1. SH for actual output = 480 × 3 = 1,440 hours; standard cost = 1,440 × 20 = ₹28,800
  2. Actual cost = 1,600 × 21 = ₹33,600; LCV = 28,800 − 33,600 = ₹4,800 (A)
  3. LRV = 1,600 × (20 − 21) = ₹1,600 (A)
  4. Idle time variance = 100 × 20 = ₹2,000 (A)
  5. Hours worked = 1,600 − 100 = 1,500; LEV = 20 × (1,440 − 1,500) = ₹1,200 (A)
  6. Check: 1,600 + 2,000 + 1,200 = ₹4,800 (A)
Answer

LCV ₹4,800 A = LRV ₹1,600 A + idle time ₹2,000 A + LEV ₹1,200 A.

Overhead variances

VarianceFormula
Variable OH expenditure(AH × standard VOH rate per hour) − actual VOH
Variable OH efficiencyStandard VOH rate per hour × (SH − AH)
Fixed OH costAbsorbed FOH (actual output × standard rate per unit) − actual FOH
Fixed OH expenditure (budget)Budgeted FOH − actual FOH
Fixed OH volumeAbsorbed FOH − budgeted FOH = standard rate per unit × (actual output − budgeted output)
Volume sub-variancesCapacity, efficiency and calendar variances

Overhead variances

Problem

(a) Variable overhead: standard rate ₹4 per hour; standard hours for actual output 2,000; actual hours 2,200; actual variable overhead ₹8,400. (b) Fixed overhead: budget ₹50,000 for 10,000 units; actual output 9,000 units; actual fixed overhead ₹52,000.

Working
  1. (a) VOH expenditure = 2,200 × 4 − 8,400 = 8,800 − 8,400 = ₹400 (F)
  2. VOH efficiency = 4 × (2,000 − 2,200) = ₹800 (A); total = 2,000 × 4 − 8,400 = ₹400 (A)
  3. (b) Standard rate = 50,000 ÷ 10,000 = ₹5 per unit; absorbed FOH = 9,000 × 5 = ₹45,000
  4. FOH cost variance = 45,000 − 52,000 = ₹7,000 (A)
  5. Expenditure variance = 50,000 − 52,000 = ₹2,000 (A); volume variance = 45,000 − 50,000 = ₹5,000 (A)
  6. Check: 2,000 + 5,000 = ₹7,000 (A)
Answer

VOH: ₹400 F expenditure + ₹800 A efficiency = ₹400 A. FOH: ₹2,000 A expenditure + ₹5,000 A volume = ₹7,000 A.

How NET asks this

NET gives standard and actual quantity, price or hours and asks for one variance with its sign, or asks you to match variances with formulas and check that the parts add up to the total.

Exam angle

Typical MCQ: “SP ₹12, AP ₹13, AQ 500 kg. What is the material price variance?” 500 × (12 − 13) = ₹500 adverse. Trap: using standard quantity instead of actual quantity.

Typical MCQ: “Can idle time variance ever be favourable?” No. It is always adverse, because hours are paid for but nothing is produced.

Remember it

Price uses Actual quantity; usage uses Standard price. Always compute standard − actual: plus is favourable, minus is adverse.