Decision theory and PERT/CPM

Decision criteria depend on what is known: certainty, risk (EMV) or uncertainty. In a project network, the critical path is the longest path and fixes the project duration.

Criteria under uncertaintyMaximax (optimist), maximin (pessimist; Wald), Hurwicz (realist; α), Laplace (equal chances), minimax regret (Savage)
EVPIExpected value with perfect information − best EMV; it also equals the minimum EOL
PERT estimatestₑ = (a + 4m + b) ÷ 6; variance = [(b − a) ÷ 6]²; based on the beta distribution
OriginsCPM: DuPont with Remington Rand, 1957. PERT: US Navy, Polaris missile project, 1958

Decision environments

EnvironmentWhat is knownTools
CertaintyThe outcome of each actPick the best payoff; linear programming
RiskThe probabilities of the statesEMV, EOL, EVPI, decision trees
UncertaintyOnly the possible states, with no probabilitiesMaximax, maximin, Hurwicz, Laplace, minimax regret
ConflictAn intelligent opponentGame theory

Criteria under uncertainty

CriterionAttitudeRule
MaximaxOptimistTake each act's best payoff; choose the highest
Maximin (Wald)PessimistTake each act's worst payoff; choose the highest
Minimax regret (Savage)Avoids regretRegret = best payoff in that state − the act's payoff; choose the act with the smallest maximum regret
HurwiczRealistα × best + (1 − α) × worst, where α is the coefficient of optimism; choose the highest
LaplaceEqual likelihoodAverage each act's payoffs (principle of insufficient reason); choose the highest

Worked example 1: one payoff table, six criteria

Problem

A Tiruppur garment exporter chooses between A1 (expand), A2 (add a shift) and A3 (no change). Payoffs in ₹ lakh for high, medium and low demand: A1 = 80, 40, −20; A2 = 60, 45, 5; A3 = 30, 30, 30. Use α = 0.6 for Hurwicz and probabilities 0.3, 0.5 and 0.2 for EMV.

Working
  1. Maximax: best payoffs 80, 60, 30, so choose A1 (80).
  2. Maximin: worst payoffs −20, 5, 30, so choose A3 (30).
  3. Hurwicz: A1 = 0.6 × 80 + 0.4 × (−20) = 48 − 8 = 40; A2 = 36 + 2 = 38; A3 = 30. Choose A1.
  4. Laplace: A1 = 100 ÷ 3 = 33.33; A2 = 110 ÷ 3 = 36.67; A3 = 30. Choose A2.
  5. Regret: column bests are 80, 45, 30. Regrets: A1 = 0, 5, 50; A2 = 20, 0, 25; A3 = 50, 15, 0. Maximum regrets 50, 25, 50, so choose A2.
  6. EMV: A1 = 24 + 20 − 4 = 40; A2 = 18 + 22.5 + 1 = 41.5; A3 = 30. Choose A2 (₹41.5 lakh).
  7. EVPI: with perfect information, 0.3 × 80 + 0.5 × 45 + 0.2 × 30 = 52.5. EVPI = 52.5 − 41.5 = ₹11 lakh, equal to A2's EOL (0.3 × 20 + 0.2 × 25 = 11).
Answer

Maximax and Hurwicz pick A1; maximin picks A3; Laplace, minimax regret and EMV pick A2. EVPI = ₹11 lakh.

Network basics

  • An activity uses time and resources; an event (node) is a point in time when activities start or end.
  • Activity-on-arrow (AOA) networks may need a dummy activity: zero time and zero resources, drawn dotted, to show logic only.
  • Fulkerson's rule numbers the events so that every arrow runs from a lower to a higher number.
  • Forward pass: ES = the largest EF of the predecessors; EF = ES + t. Backward pass: LF = the smallest LS of the successors; LS = LF − t.
  • Total float = LS − ES = LF − EF. Free float = earliest start of the successors − EF. Independent float ≤ free float ≤ total float.
  • Critical activities have zero total float. The critical path is the longest path, and there can be more than one.

PERT vs CPM

PERTProbabilistic: three time estimates (optimistic a, most likely m, pessimistic b) and a beta distribution. Event-oriented. Suits new, uncertain work such as R&D.
CPMDeterministic: one time estimate per activity. Activity-oriented. Suits repeat projects such as construction, and allows a time-cost trade-off (crashing).

Worked example 2: critical path and floats

Problem

Activities (days) and their predecessors: A 3 (none), B 4 (none), C 2 (A), D 6 (A), E 3 (B, C), F 4 (D, E). Find the critical path, the project time and the floats.

Working
  1. Paths: A-D-F = 3 + 6 + 4 = 13; A-C-E-F = 3 + 2 + 3 + 4 = 12; B-E-F = 4 + 3 + 4 = 11.
  2. Forward pass (ES, EF): A 0, 3; B 0, 4; C 3, 5; D 3, 9; E starts at max(4, 5) = 5 and ends at 8; F starts at max(9, 8) = 9 and ends at 13.
  3. Backward pass (LS, LF): F 9, 13; E 6, 9; D 3, 9; C 4, 6; B 2, 6. For A, LF = min(4, 3) = 3, so LS = 0.
  4. Total float (LS − ES): A 0, B 2, C 1, D 0, E 1, F 0.
  5. Free float: B = ES of E − EF of B = 5 − 4 = 1; C = 5 − 5 = 0; E = 9 − 8 = 1.
Answer

The critical path is A-D-F, 13 days. B can slip 2 days without delaying the project, but only 1 day without delaying E.

Worked example 3: PERT time and probability

Problem

The critical path has three activities with (a, m, b) in days: P (2, 5, 14), Q (4, 7, 16), R (3, 6, 9). Find the expected project time and the chance of finishing within 26 days.

Working
  1. tₑ: P = (2 + 20 + 14) ÷ 6 = 6; Q = (4 + 28 + 16) ÷ 6 = 8; R = (3 + 24 + 9) ÷ 6 = 6. Project Tₑ = 20 days.
  2. Variances [(b − a) ÷ 6]²: P = (12 ÷ 6)² = 4; Q = (12 ÷ 6)² = 4; R = (6 ÷ 6)² = 1. Project variance = 9, so σ = 3 days.
  3. z = (26 − 20) ÷ 3 = 2. The area up to z = 2 is 0.9772.
  4. For 23 days: z = (23 − 20) ÷ 3 = 1, giving 0.8413.
Answer

Expected time 20 days and σ = 3 days. P(finish within 26 days) ≈ 97.72%; P(within 23 days) ≈ 84.13%.

How NET asks this

NET gives a small payoff table and asks which act each criterion picks (maximax, maximin, Hurwicz, Laplace, regret, EMV), or a short network and asks for the critical path, floats, PERT tₑ and variance, and the probability of finishing on time.

Exam angle

Typical MCQ: “Activity times are a = 4, m = 7 and b = 16. Find tₑ and its variance.” tₑ = (4 + 28 + 16) ÷ 6 = 8; variance = (12 ÷ 6)² = 4. Trap: using the simple average (9), or giving σ = 2 as the variance.

Typical MCQ: “Which criterion uses a coefficient of optimism?” Hurwicz. Trap: Laplace uses equal probabilities and Savage uses regret.

Typical MCQ: “Three critical activities have SDs of 1, 2 and 2 days. What is the project SD?” Variance = 1 + 4 + 4 = 9, so σ = 3 days. Trap: adding the SDs to get 5.

Remember it

Optimist: maximax. Pessimist: maximin. Realist: Hurwicz. Fair-minded: Laplace. Regretful: Savage. In PERT, add variances, never SDs.