haya.Learning made clear
Unit V · Valuation, investment and working capital
12 min readConcept sheetMCQ · NPV, IRR and payback numericals; method match

Capital budgeting: methods, comparison and risk analysis

Capital budgeting judges long-term projects. NPV is the gold standard: accept if it is positive. IRR, PI and payback help, but can mislead on mutually exclusive projects.

NPVPV of inflows − outlay; accept if NPV > 0. Additive; assumes reinvestment at the cost of capital
IRRThe rate that makes NPV = 0; accept if IRR > cost of capital
PI (benefit-cost ratio)PV of inflows ÷ outlay; accept if PI > 1
PaybackYears to recover the outlay; ignores time value and cash flows after payback

The capital budgeting process

Use cash flows, not accounting profits: incremental and after tax. Ignore sunk costs; include opportunity costs and changes in working capital.

Methods compared

MethodFormula and ruleTime value?Main weakness
PaybackOutlay ÷ annual inflow (even flows); accept if within the targetNoIgnores time value and cash flows after payback
Discounted paybackYears for cumulative PV of inflows to cover the outlayYesStill ignores cash flows after payback
ARR (accounting rate of return)Average profit after tax ÷ average investmentNoUses accounting profit, not cash flow
NPVPV of inflows − outlay; accept if > 0YesNeeds a known discount rate; gives an amount, not a rate
IRRRate at which NPV = 0; accept if > cost of capitalYesMultiple IRRs possible; assumes reinvestment at the IRR
PIPV of inflows ÷ outlay; accept if > 1YesCan mis-rank projects of different sizes

Worked example 1: NPV, PI, payback and discounted payback

Problem

A project costs ₹1,00,000. Cash inflows are ₹40,000, ₹40,000, ₹30,000 and ₹30,000 in years 1 to 4. The cost of capital is 10%. Find NPV, PI, payback and discounted payback. (PVs are rounded to the nearest rupee.)

Working
  1. PVs: 40,000 ÷ 1.1 = 36,364; 40,000 ÷ 1.21 = 33,058; 30,000 ÷ 1.331 = 22,539; 30,000 ÷ 1.4641 = 20,490.
  2. Total PV = 36,364 + 33,058 + 22,539 + 20,490 = ₹1,12,451.
  3. NPV = 1,12,451 − 1,00,000 = ₹12,451. PI = 1,12,451 ÷ 1,00,000 = 1.12.
  4. Payback: 40,000 + 40,000 = 80,000 after 2 years; the remaining 20,000 comes from year 3's 30,000, so payback = 2 + 20,000 ÷ 30,000 = 2.67 years.
  5. Discounted payback: adding the rounded PVs, cumulative PV is 69,422 after 2 years and 91,961 after 3 years. Remaining 8,039 ÷ 20,490 = 0.39, so 3.39 years.
Answer

NPV ₹12,451 (accept), PI 1.12, payback 2.67 years, discounted payback 3.39 years. Discounted payback is always longer than simple payback.

Worked example 2: IRR by interpolation, and ARR

Problem

A machine costs ₹1,00,000 and yields ₹30,000 a year (after tax, before depreciation) for 5 years, with no salvage value. The cost of capital is 10%. Find payback, NPV, IRR and ARR (straight-line depreciation).

Working
  1. Payback = 1,00,000 ÷ 30,000 = 3.33 years.
  2. NPV = 30,000 × PVIFA(10%, 5) − 1,00,000 = 30,000 × 3.7908 − 1,00,000 = 1,13,724 − 1,00,000 = ₹13,724.
  3. IRR: find the 5-year PVIFA values around the payback figure 3.3333: 3.3522 at 15% and 3.2743 at 16%.
  4. IRR = 15% + (3.3522 − 3.3333) ÷ (3.3522 − 3.2743) × 1% = 15% + (0.0189 ÷ 0.0779) × 1% = 15.24%.
  5. ARR: depreciation = 1,00,000 ÷ 5 = 20,000; average profit = 30,000 − 20,000 = 10,000; average investment = (1,00,000 + 0) ÷ 2 = 50,000; ARR = 10,000 ÷ 50,000 = 20%.
Answer

Payback 3.33 years, NPV ₹13,724, IRR ≈ 15.24% (above 10%, so accept), ARR 20%.

NPV vs IRR: when they conflict

Why rankings differFor mutually exclusive projects, NPV and IRR can rank differently when the projects differ in size (scale), in the timing of cash flows, or in life.
Reinvestment assumptionNPV assumes interim cash flows are reinvested at the cost of capital; IRR assumes reinvestment at the IRR itself, which is usually unrealistic.
Fisher's rateThe discount rate at which the NPV profiles of two projects cross. Below it the two methods rank the projects differently; above it they agree.
ResolutionPrefer NPV: it measures the rupee addition to wealth. Modified IRR (MIRR) fixes the reinvestment flaw. Non-conventional cash flows can give multiple IRRs.

For independent projects with conventional cash flows, NPV, IRR and PI always give the same accept or reject decision.

Handling risk and uncertainty

TechniqueHow it works
Sensitivity analysisChange one variable at a time (sales, price, cost) and watch NPV; shows the critical variables
Scenario analysisChange several variables together under pessimistic, most likely and optimistic cases
Certainty equivalentMultiply each risky cash flow by a coefficient α (0 to 1, lower for riskier flows), then discount at the risk-free rate
Risk-adjusted discount rateDiscount at the risk-free rate + a risk premium; penalises distant cash flows more
Decision treeMaps sequential decisions and chance events with probabilities; roll back to find the expected NPV
SimulationMonte Carlo: draw values for many variables at random to get a distribution of NPV (David Hertz, 1964)
Statistical measuresExpected NPV, standard deviation and coefficient of variation of NPV

Worked example 3: certainty equivalent

Problem

A project costs ₹80,000 and is expected to give ₹50,000 in each of years 1 and 2. The certainty-equivalent coefficients are 0.9 and 0.8, and the risk-free rate is 6%. Accept or reject?

Working
  1. Certain cash flows: 50,000 × 0.9 = 45,000; 50,000 × 0.8 = 40,000.
  2. PV at 6%: 45,000 ÷ 1.06 = 42,453; 40,000 ÷ 1.1236 = 35,600.
  3. NPV = 42,453 + 35,600 − 80,000 = −₹1,947.
Answer

Reject. Ignoring risk and discounting ₹50,000 a year at 6% would wrongly show a positive NPV of ₹11,670.

How NET asks this

NET asks quick numericals (payback, NPV, PI, ARR, IRR by interpolation), which method ignores time value, the NPV-IRR conflict and reinvestment assumption, and matching risk techniques with their logic.

Exam angle

Typical MCQ: “Which two methods ignore the time value of money?” Simple payback and ARR. Trap: discounted payback does use time value, but it still ignores cash flows after payback.

Typical MCQ: “For two mutually exclusive projects, NPV favours X and IRR favours Y. Which do you choose?” X, the higher NPV: NPV measures the addition to shareholders' wealth and assumes a realistic reinvestment rate.

Typical MCQ: “Under the certainty-equivalent method, which rate discounts the adjusted cash flows?” The risk-free rate, because risk is already removed from the cash flows. Using a risk-adjusted rate as well would count risk twice.

Remember it

NPV > 0 ⇔ PI > 1 ⇔ IRR > k for a normal project. Payback and ARR are the two 'no time value' methods. In a clash, NPV wins.