Unit VIII · Statistics, operations and operations research
11 min readConcept sheetMCQ · guru match, chart choice, DMAIC sequence

Quality management: SQC, TQM, Six Sigma and ISO 9000

Quality is built in, not inspected in. SQC uses control charts and acceptance sampling; TQM, kaizen, benchmarking, Six Sigma and ISO 9000 make quality everyone's continuous job.

Quality gurusDeming: PDCA, 14 points. Juran: quality trilogy, fitness for use. Crosby: zero defects, 'quality is free'. Ishikawa: fishbone diagram, quality circles
Control chartsWalter Shewhart, Bell Labs: first control chart in a 1924 memo, book in 1931; limits at the centre line ± 3σ
Six Sigma3.4 defects per million opportunities; DMAIC; started at Motorola in 1986 (engineer Bill Smith)
ISO 9001The only certifiable standard in the ISO 9000 family; it sets the requirements for a quality management system

Quality gurus and their ideas

GuruKey contribution
W. Edwards Deming14 points for management; PDCA (Deming or Shewhart) cycle; reducing variation; seven deadly diseases
Joseph JuranQuality trilogy (planning, control, improvement); 'fitness for use'; Pareto's vital few and trivial many
Philip CrosbyZero defects; 'Quality is Free' (1979); quality as conformance to requirements; cost of quality
Kaoru IshikawaCause-and-effect (fishbone) diagram; quality circles; seven basic QC tools
Armand FeigenbaumTotal quality control; the 'hidden plant' lost to rework
Genichi TaguchiQuality loss function; robust design
Shigeo ShingoPoka-yoke (mistake-proofing); SMED (quick changeover)
Walter ShewhartControl charts; statistical process control

Control charts

ChartData typeTracksBased on
x̄ chartVariables (measured)Process averageNormal; limits x̿ ± A₂R̄
R chartVariablesProcess spread (range)Limits D₃R̄ and D₄R̄
p chartAttributes (good or bad)Fraction defectiveBinomial; p̄ ± 3√[p̄(1 − p̄) ÷ n]
np chartAttributesNumber defectiveBinomial
c chartAttributes (count of defects)Defects per unitPoisson; c̄ ± 3√c̄
u chartAttributesDefects per unit when the unit size variesPoisson

Chance vs assignable causes

Chance (common) causesMany small, random sources of variation built into the process. A process with only these is in statistical control.
Assignable (special) causesIdentifiable sources such as a worn tool or a new operator. They push points outside the control limits and must be found and removed.

Worked example 1: x̄ and R chart limits

Problem

Samples of 5 bearings give a grand mean x̿ = 50 mm and an average range R̄ = 4 mm. For n = 5, A₂ = 0.577, D₃ = 0 and D₄ = 2.114. Find the control limits.

Working
  1. x̄ chart: UCL = 50 + 0.577 × 4 = 50 + 2.308 = 52.308 mm; LCL = 50 − 2.308 = 47.692 mm.
  2. R chart: UCL = D₄R̄ = 2.114 × 4 = 8.456 mm; LCL = D₃R̄ = 0 × 4 = 0.
Answer

x̄ chart: 47.692 to 52.308 mm (centre 50). R chart: 0 to 8.456 mm (centre 4).

Worked example 2: p chart limits

Problem

20 samples of 100 units each contain 80 defectives in all. Find the limits of the p chart.

Working
  1. p̄ = 80 ÷ (20 × 100) = 0.04.
  2. σp = √[0.04 × 0.96 ÷ 100] = √0.000384 = 0.0196 (4 decimal places).
  3. UCL = 0.04 + 3 × 0.0196 = 0.0988. LCL = 0.04 − 0.0588 = −0.0188, which is set to 0.
Answer

Centre 0.04, UCL ≈ 0.0988, LCL = 0 (a negative limit is taken as zero).

Acceptance sampling

  • Inspect a random sample from a lot. Accept the lot if the defectives are at most the acceptance number c; otherwise reject it. Used when 100% inspection is costly or destructive.
  • Plans: single, double, multiple and sequential sampling.
  • The operating characteristic (OC) curve shows the probability of accepting lots of each quality level.
  • Producer's risk (α): a good lot, at the AQL, is rejected. Consumer's risk (β): a bad lot, at the LTPD, is accepted.
  • AOQL is the worst average outgoing quality after rejected lots are screened. Dodge and Romig published standard sampling tables.

TQM and continuous improvement tools

ConceptCore ideaLinked with
TQMCustomer focus, involvement of every employee, a process approach and continuous improvement across the whole organisationDeming, Juran, Feigenbaum
KaizenSmall, continuous improvements by everyone, every day, at the workplace (gemba)Masaaki Imai (1986); Toyota
Quality circleA small group of workers from the same area meets voluntarily and regularly to solve work problemsIshikawa; Japan, 1962
BenchmarkingCompare processes with the best in class and adopt better practices; internal, competitive, functional or genericXerox (1979); Robert Camp
5SSort, set in order, shine, standardise, sustain (seiri, seiton, seiso, seiketsu, shitsuke)Japanese workplace practice
Poka-yokeMistake-proofing, so an error cannot happen or is caught at onceShigeo Shingo
Cost of qualityPrevention and appraisal costs (good quality) vs internal and external failure costs (poor quality)Juran, Crosby

Six Sigma DMAIC

DMAIC improves an existing process; DMADV (define, measure, analyse, design, verify) designs a new one. Roles include Champion, Master Black Belt, Black Belt and Green Belt.

Worked example 3: DPMO

Problem

A bank processes 1,000 loan files, each with 5 chances of error (opportunities). Auditors find 50 errors. Find the defects per million opportunities.

Working
  1. Total opportunities = 1,000 × 5 = 5,000.
  2. Defects per opportunity = 50 ÷ 5,000 = 0.01, a yield of 99%.
  3. DPMO = 0.01 × 10,00,000 (one million) = 10,000.
Answer

10,000 DPMO, far from the Six Sigma target of 3.4.

The ISO 9000 family

StandardWhat it is
ISO 9000Fundamentals and vocabulary of quality management systems
ISO 9001Requirements for a QMS; the only one used for certification
ISO 9004Guidance for sustained success beyond the basic requirements
ISO 19011Guidelines for auditing management systems

ISO points to remember

  • ISO was founded in 1947 and is based in Geneva. It first issued the ISO 9000 series in 1987. In India, BIS publishes it as IS/ISO 9000.
  • Seven quality management principles: customer focus, leadership, engagement of people, process approach, improvement, evidence-based decision making and relationship management.
  • Accredited third-party bodies certify firms; ISO itself does not certify.
  • ISO 14001 (environment) and ISO 45001 (occupational health and safety) are separate standards, not part of the ISO 9000 family.
How NET asks this

NET asks you to match gurus with ideas, choose the right control chart (x̄, R, p, np, c), sequence DMAIC, separate producer's and consumer's risk, and know which ISO 9000 standard is certifiable. Short p-chart or DPMO sums also appear.

Exam angle

Typical MCQ: “What is the producer's risk?” The probability of rejecting a good lot (at the AQL); it is α. The consumer's risk β is accepting a bad lot (at the LTPD). Trap: swapping the two.

Typical MCQ: “Which chart tracks the number of defects on each car door panel?” The c chart (Poisson). Trap: the p chart is for the fraction of defective units, not counts of defects.

Typical MCQ: “Which ISO standard are firms certified to?” ISO 9001. Trap: ISO 9000 covers only fundamentals and vocabulary.

Remember it

DMAIC = 'Do Many Analysts Improve Continuously': Define, Measure, Analyse, Improve, Control. c for counts, p for proportions.